"Construction of PU Synthetic Surface for Handball Court at HSS Sholipora-Budgam"

"Construction of PU Synthetic Surface for Handball Court at HSS Sholipora-Budgam"



LUPCODE
Name of the Project
District
Amount Approved in HPC
Current Physical Progress
YSS1049
Construction of PU Synthetic Surface for Handball Court at HSS Sholipora-Budgam
Budgam
0.77360 crore
35%

Images of the Languishing Project (Current Status)


Current Progress